Intro
Will you generate electricity on the coldest winter nights or hottest summer days?
Many power plants receive natural gas "just in time" via pipelines. They have little to no fuel storage. Not even many "black start" power plants.
Winter storms disrupt gas pipeline deliveries. Natural gas storage at power plants enhances electricity security.
EnergyFlex Ventures can help you permit, build, and operate LNG and PLNG fuel storage which can power your electricity for days.
We bring “Energy Storage as a Service”
Project and Operations Management
-
Project formation
-
Permitting
-
Design and Construction Management
-
Operations
Data Centers, Manufacturing, Municipal Utilities, or baseload Combined Cycle …
We right-size a fuel storage solution to match your electricity-assurance exposure.
-
Days of fuel storage as Pressurized LNG (PLNG) at Reduced GHGe
-
Scope 1 by 90+%
-
Scope 2 by 25-35%
Proprietary Technology
Problem
Regional Power Reliability
WINTER STORM URI
• 200+ fatalities
• Texas, February, 2021
WINTER STORM ELLIOTT
• 10 Bcf/d knocked offline.
• North East US, December, 2022
CYBER ATTACK
• Colonial Pipeline, May 7 to 15, 2021.
• 10,600 stations without gasoline on May 18
ERCOT “Conservation Appeal”
• Summer 2023 and January 2024
Solution
Gas Storage for better Electrical Grid Resilience
-
Liquified Natural Gas (LNG)
-
Proven technology widely deployed for decades for gas distribution
-
Proven paths to obtaining permits using conventional bullets and tanks
-
LNG by truck for up to 50 MW power generation capacities
-
Produce LNG on site for 100 to 1000+ MW, can consider trucked LNG sales.
-
-
Pressurized Liquified Natural Gas (PLNG) at 10 to 16 atmospheres / bar-g.
-
30-45 % less energy than LNG
-
Reduced GHGe (Scope 1 by 90+%, Scope 2 by 25-35%) versus
unpressured LNG
-
Permitting Benchmarks (by others)
LNG Facilities to “Stockpile” Energy
Northeast Energy Center (NEC), Charlton, Massachusetts: 5.5 year project life cycle
-
Operations April 1, 2024. “First Petition” to construct August 31, 2018
-
Project Components: Gas pretreatment; Liquefaction at 250,000 gallons per day; 2-million gallon full-containment; field-erected LNG storage tank; Four bay LNG truck-loading station
Desktop screening study: LNG storage facility at a power generation company (GenCo) site in Texas.
-
Project schedule of three years was possible (Front End Engineering & Design for permitting deliverables to Operations)
-
Approvals required from over 20 entities (regulatory agency, other approving authority, or utility provider)
Permitting
LNG Facilities to “Stockpile” Energy
Northeast Energy Center (NEC), Charlton, Massachusetts: 5.5 year project life cycle
• Operations April 1, 2024. “First Petition” to construct August 31, 2018
• Project Components: Gas pretreatment; Liquefaction at 250,000 gallons per day; 2-million gallon full-containment; field-erected LNG storage tank; Four bay LNG truck-loading station
Desktop screening study: LNG storage facility at a power generation company (GenCo) site in Texas.
• Project schedule of three years was possible (Front End Engineering & Design for permitting deliverables to Operations)
• Approvals required from over 20 entities (regulatory agency, other approving authority, or utility provider)
What We Provide
01
Project Design
Describe the service and how customers or clients can benefit from it. It’s an opportunity to add a short description with relevant details, like pricing, duration and how to book.
02
Construction Management
Describe the service and how customers or clients can benefit from it. It’s an opportunity to add a short description with relevant details, like pricing, duration and how to book.
03
Site Evaluation
Describe the service and how customers or clients can benefit from it. It’s an opportunity to add a short description with relevant details, like pricing, duration and how to book.
04
Construction
Describe the service and how customers or clients can benefit from it. It’s an opportunity to add a short description with relevant details, like pricing, duration and how to book.
05
Cost Modeling
Describe the service and how customers or clients can benefit from it. It’s an opportunity to add a short description with relevant details, like pricing, duration and how to book.
President
Don Victory
ENERGYFLEX VENTURES LLC
Don Victory retired as the Upstream Chief Process Engineer at ExxonMobil after a 40 year career that included being on the Governing Body of Gastech. Don co-chaired with Chris Caswell at LNG2019 in Shanghai, “LNG Forum: Technical Innovation for the Future of LNG.”
Don is the Founder and Chair of Energy Mentors, a 501(c)(3) charity sponsoring “Power the Community - an International College Design Competition” to design affordable, reliable, and sustainable energy for a community of 2,000 families affordable on the combined salaries of a nurse and a schoolteacher. Students have the potential to win a $10,000 grand prize of a total prize pool of $31,000. Don is also a Founder of EnergyFlex Ventures, LLC, which has a mission of providing Energy Storage as a Service to enhance energy resilience.